Hayley Dingle Phase 2

In 2009 Worcestershire GLASS volunteers carried out improvements to drainage.

Materials and tools were supplied by Worcestershire County Council:
• Tracked 8 tonne 360° Excavator
• Wheeled dump truck
• Pavement roller
• Drainage tube
• Stone

The surface of the lane was dug away to bury the drainage tube which exits into a pre-existing culvert. The resulting trench was backfilled with stone and then compacted with the vibrating roller to consolidate the repair.

The plant operator was a GLASS member with the necessary qualifications to work on the public highway.

© 1995 - 2020 Green Lane Association Ltd